 |
Hampton Forest Apartments located in Greenville, South Carolina
This was a two story building which comprised of 40 apartment units, corridors and other common areas. This building had detectable levels of asbestos in the acoustical spray applied ceiling, drywall joint compound on ceilings and walls and multi-layer flooring materials located in the kitchens, restrooms and common laundry rooms.
This facility was severely damaged by a fire that broke out in the end of the building which affected units 101 through 106 on the 1st floor and 201 through 206 on the second floor. These units were damaged beyond repair and as such were demolished leaving the concrete slab. All demolished materials were direct loaded into lined waste containers and disposed of as asbestos containing/contaminated.
The immediately adjoining the demolished units (107, 108, 207 & 208) had all of the drywall (walls & ceilings) and multi-layer flooring removed leaving the framing. This allowed for further investigation by the project engineer to determine structural soundness. This work was performed utilizing full negative pressure containments. The waste generated as part of this process was bagged and properly disposed of.
The remaining units 209, 210, 211, 212, 213, 214, 215, 216, 217, 218, 219 & 220) suffered a combination of smoke and water damage as a result of putting out the fire. In these units a combination of ceiling, lower 4 feet of walls and multi-layer flooring were abated utilizing full negative pressure containments and wet methods. The waste generated as part of this process was bagged and properly disposed of.
CCI worked with the City of Greenville to obtain proper permits and subcontracted with Britt, Peters and Associates, Inc. to prepare the site erosion control plan which we installed and maintained for
the duration of the project.
S&ME of Greenville, SC provided air monitoring for the project.
There were approximately 18 employees on site for a period of 60 days
Project Value: $ 198,030.00
Arly Manufacturing Building;
Mathews NC
10701 Monroe Rd
Mathews, NC
$640,000.00
Scope Summary: Complete asbestos abatement on 60,090 sqft of asbestos containing floor tile and drywall. Complete demolition of 250,000 sqft manufacturing building.
Asbestos Removal and Structual Demolition
1229 Greenwood Cliff RD
Charlotte, NC
$150,000.00
Owner: Charlotte Real Estate Ass.
CCI – Contractor
Scope Summary: The removal of positive identified asbestos containing material (roof flashing, floor tile, carpet and black mastic), The demolition of structure, leaving 1st floor slab and retaining wall.
.
WCU Harrill Residence Hall
GC – New Atlantic Contracting
Asbestos Abatement
Western Carolina University
Cullowhee, NC
$209.000.00
CCI successfully removed asbestos containing materials in floor tiles, mastic, ceiling surfacing, pipe insulation, pipe elbows and tank insulation in the Harrill Hall Residence. Demolition was completed on walls, ceilings, light fixtures, doors, carpet, ceramic tile, radiators, louvers, windows throughout the residence. In addition to the interior demolition work, exterior sidewalks and walkways were also removed.
|
 |
 |