DEMOLITION PROJECTS

SHERWIN WILLIAMS PLANT DECOMMISSIONING OLIVE BRANCH, MS

DISMANTLING AND DEMOLITION: CCI completed the decommissioning, demolition and industrial cleaning of one of the largest paint producing plants in the South East. This was an accelerated schedule with 40% of the plant still in operation. Project consisted of numerous hours of dismantling and rigging operations in confined areas. All chemicals were drummed, labeled, and packaged for proper shipping. 95% of all materials on-site were recycled and diverted from local land fills. With a scope of work as follows:

    • Dismantling and salvage for owner of over 200 holding and mixing tanks. • Complete demolition of the Cooker Building and Tank Farm
    • Interior dismantling, demolition and salvage for owner of the mixing tank mezzanine and all tanks.
    • Asset recovery near $8 million dollars worth of production equipment and tanks
    • Removal of all overhead process lines and non-essential building mechanical, electrical and plumbing systems.

    ENVIRONMENTAL AND INDUSTRIAL CLEANING:
    • The work included the cleaning and removal of all hazardous and nonhazardous chemical liquids from over 200 holding and mixing tanks. The blasting of containment pads, trenches, piping and equipment to prepare for demolition.
    • Management of Lead-Based Paint, Fluorescent Light Tubes, PCB Transformers, and Hazardous Liquidsted all tasks on schedule, on budget, and with no OSHA incidents.

DEMOLITION OF VILLA ST MAURICE NEW ORLEANS, LA

CCI completed the separation, demolition and recycling of 2 five story post tensioned concrete frame buildings and the selective interior demolition of the remaining attached 4 story. The demolition was complicated by the proximity of the adjacent remaining 4 story historical building that was actually attached to a portion of one of the buildings. CCI performed vibration monitoring and modified normal working procedures to ensure the neighboring historic residential homes were not damaged during the demolition. CCI also performed restoration work at the location of the separation from the 4 story. 97% of all materials on-site were recycled. Diverting over 21,000 tons from local land fills.
With a scope of work as follows:

    • Interior demolition and removal of non-recyclable building materials from over 140,000 sf.
    • Separation and dismantling of the 4 story attached concrete portion.
    • Restoration of historic 4 story at point of separation.
    • Complete demolition of the two 5 story buildings totaling over 110,000sf
    • Removal of select pavements and large building concrete pile caps and grade beam foundations.
    • Installation of 8’ permanent site fence.
    • Site restoration including soil import, site grading and green turf establishment.

DEMOLITION OF ST MARTINS MANOR NEW ORLEANS, LA



CCI demolished the 5 story 57,000 sf concrete post tensioned structure down to the concrete pilings. CCI successfully dismantled the last 3 bays that were adjacent within 10’ to 3 historical statues to the North and 15’ to the West of an 1890’s 2 story historic rectory and 20’ to the South along the entire 300’ long front of an 1890’s historic brick wall. All adjacent structures were left in place with no resulting damage. CCI recycled 93% of the entire demolition material generated. The resulting recycling efforts diverted over 9,000 tons from local landfills.

PACIFIC COAST FEATHER MILL DEMOLITION HENDERSON, NC


CCI completed the dismantling, demolition and asbestos abatement of the RSM textile manufacturing plant after it was damaged from fire. The project consisted of numerous hours of dismantling and rigging operations to separate remaining portions of the plant from the damaged portions which included flying roof top dust collection and drying units from the remaining structures. The asbestos and chemical removal included abatement of structurally sound portions and gross clean up and intact demolition of unstable structures.
With a scope of work as follows:
    • Dismantling and demolition of over 275,000 sf.
    • Abatement of floor tile and mastic, ceiling insulation, pipe insulation and transite paneling. Chemicals include pcb transformers, cleaning solvents and process liquids.
    • Separation of 780lf of manufacturing plant structure and equipment. Segregation and recycling of over 2,500 tons of ferrous and non-ferrous metals.

PATTERSON HALL DORM RENOVATION

CCI completed the building dismantlement, demolition and abatement of the 11 story concrete and steel building. This was a closely coordinated project between the asbestos and universal waste abatement, the dismantling of the top floors and the demolition down to the remaining structural frame while the renovation trades worked on adjacent floors. Project consisted of numerous hours of dismantling and rigging operations of the top floors and penthouses. Saw cutting and removal of select load bearing columns and slabs. All asbestos, lead and universal wastes were removed while still maintaining a strict recycling requirement.
With a scope of work as follows for the 115,000 sf structure:

    • Asbestos abatement of floor tile and mastic, ceiling texture, mastic adhesives and pipe insulation all through out the structure.
    • Complete dismantle and removal of the eleventh floor and penthouse structures.
    • Interior demolition of all finishes, mechanical, electrical, plumbing and fire protection equipment.
    • Removal of all exterior walls, elevators, stair wells and shafts.
    • Removal of exterior site paving, courtyard structures and planters.

DEMOLITION OF CENTRAL CHEMICAL PLANT HAGGERSTOWN, MD

CCI was contracted to start work at the Central Chemical Plant which was historically used as a pesticide formulation (DDT) facility.
With a scope of work as follows:

    • Decontamination & cleaning of 17 structures affected by the pesticide dust and miscellaneous chemicals.
    • Engineered a super-vac equipped with a high efficiency particulate filter (HEPA) exhaust and plenum system for proper dust particle removal.
    • Surveying and removal of all asbestos containing materials.
    • Structural demolition and dismantling of 17 structures of various sizes to include the dismantling of a 12 story industrial facility.
    • Management of Lead-Based Paint, Fluorescent Light Tubes, PCB Transformers, and Hazardous Liquids.


 

Contaminant Control, Inc.
3434 Black & Decker Rd. Hope Mills, NC 28348

1-800-815-0085