DEMOLITION PROJECTS

Central Chemical; Hagerstown, MD

CCI was contracted to remove dust and debris from 17 structures at the Central Chemical Superfund Site in Hagerstown, Maryland followed by demolition of the buildings. The site was used primarily as a pesticide formulation (DDT) facility; some of the buildings were used for miscellaneous tasks such as automotive repair, metal machining, chemical storage, and wood working. CCI performed an asbestos survey and pre-characterized the wastes prior to commencing siteoperations. CCI started by removing the asbestos and gross removal of the contaminated dust. CCI also configured a super-vac equipped with a High Efficiency Particulate Filter (HEPA) exhaust and a plenum system to equip the technicians with a dust removal system. With all the debris and dust removed, CCI initiated site preparation to include erosion and sedimentation controls, designation of stockpile areas, and delineation of decontamination areas. More than 400 tons of general debris was removed prior to demolition of the 17 buildings. CCI sampled, analyzed, and characterized 638 cubic yards of Subtitle C hazardous waste and 165 tons of Subtitle D non-hazardous waste prior to containerizing the waste for transport to pre-approved disposal facilities. An additional 175 tons of abatement-containing materials was removed, packaged, and disposed. More than 550 tons of structural steel was decontaminated and transported off site for recycling at a pre-approved facility. CCI completed all tasks on schedule, on budget, and with no OSHA incidents.

Lake Front Airport

CCI was hired to perform, temporary interior protection of surfaces to remain, selective interior demolition and historical salvage on designated furnishings throughout the two story historical building.

The project included the removal and disposal of interior drywall walls and associated studs back to the original finishes, drywall ceilings and associated support systems, interior floor finishes and associated adhesives other interior finishes such as wainscot, cove base, crown moldings and door & doorjambs (where not slated for salvage) and Mechanical Electrical & Plumbing (MEP) back to the nearest point of connection. CCI perform removal for salvage interior furnishings such as toilets/urinals sanitized, toilet stalls/doors, 125 each door/doorjamb and overhead transoms. The project was completed within 6 weeks.

U.S. Customs House Selective Demolition
The renovation was due to extension damage caused by Hurricane Katrina.  CCI was contracted by Woodward Design Build, for the interior demolition at the US Customs House, New Orleans, La. The interior demolition included demolition and removal of ductwork, air handlers and plumbing. It also included removal of interior partition walls, ceilings, floor coverings, doors and frames, portions of rotten wood flooring, wall tile, existing former light shafts, ceiling removal on certain floors, demo and removal of HVAC concrete housekeeping pads. Demolition of multiple brick walls was also accomplished.

Due to the historical nature and value of the US Customs House, much of the demolition had to be done by hand. Trash Chutes were constructed on the outside of the building and ramps were built on the inside for debris to be dropped from the 2nd, 3rd and 4th floors. In order to preserve the pavers / sidewalks, CCI utilized plywood as a covering for protection of the pavers / sidewalks.

CCI provided temporary barricades and other protection to ensure a safe working area, not only for our employees, but for the many other contractors working in the area. CCI also provided dust control measures during the demolition phase, provided disposal of all of the debris removed.

Demolition and Emergency Response; Kinston, NC

CCI personnel responded in connection to a plant explosion in North Carolina. CCI was called to respond in two different capacities.  The first was in an emergency response capacity and the second was to perform demolition of the damaged structure.  CCI provided complete demolition and disposal of approximately 40,000 square feet of the warehouse portion of the plant.  Demolition was performed utilizing hydraulic shears and grapples on hydraulic excavators.  Stored materials from the damaged warehouse, as well as the structure itself, were segregated and staged using heavy equipment. CCI performed demolition of approximately 1,132 tons of construction debris, steel, and concrete.

Propane Decontamination and Demolition; Chesapeake, VA

The 38-acre former Smith Douglas bulk fertilizer facility located on the Elizabeth
River in Chesapeake, Virginia shipped and received various agricultural and
commercial fertilizers by barge, rail, and truck traffic. On-site chemicals included
industrial fertilizers, PCBs, and asbestos. The facility operated as a blending,
manufacturing, and bagging operation. The project goal was to restore the property for future development by the Peak Shaving LNG/Propane distribution facility. CCI’s scope of work consisted of utility abandonment, asbestos abatement, building demolition, barge dock demolition, rail service demolition, waste sampling and packaging, mass excavation, soil segregation and load-out, erosion control feature installation including sediment basins and diversion dikes, UST removal and closure, and backfilling/compaction/finish grading operations including seeding and straw placement.

The project involved demolition of five buildings that totaled approximately 80,000 square feet. Flat slab concrete structures/slabs/footings demolition included approximately 540,000 square feet. CCI’s tasks included:

  • Asbestos Abatement/Excavation
  • Unknown Container Sampling, Containerization, Transportation, and Disposal
  • Miscellaneous Floor and Site Debris Management, Transportation, and Disposal
  • Management of Lead-Based Paint, Fluorescent Light Tubes, PCBs, and Hazardous Liquids
  • Hazardous and Non-Hazardous Soil Excavation, Transportation, and Disposal
  • Hazardous and Non-Hazardous Pesticide Waste Management
  • Site Re-grading.

Hampton Forest Apartments Greenville, SC

This project was a result of a fire which broke out in building A of the Hampton
Forest Apartments facility. Asbestos was found to be contained within the spray
applied acoustical ceiling, drywall joint compound and flooring materials. The
fire damage was significant in nature where as it affected 12 apartments total
and as a result CCI demolished this section of the building down to the existing
slab. The remaining 1st floor apartments were gutted of all acoustical ceiling
material, flooring and drywall walls and ceilings. The 2nd floor had only the
acoustical ceiling materials removed.  Burned area all interior surfaces &
remaining personal items 12 Apartments.

Project Totals are as follows: 
 
  • Flooring Materials
  • Acoustical Ceiling Material Only
  • Acoustical Ceiling & Associated Drywall 
  • Drywall Wall
  • Project Duration:  

6,360 SF.
10,730 SF.
14,734 SF.
61,776 SF.
7 weeks


 

 

 

 

 

Contaminant Control, Inc.
3434 Black & Decker Rd. Hope Mills, NC 28348

1-800-815-0085