Building 487 Mold Remediation, Pope AFB, NC
Building 487 is a hotel utilized to house Air Force personnel during
assignments at Pope AFB. A water pipe burst on a weekend and
was not discovered until early the next Monday morning. The Air
Force was slow in responding to the incident and an extensive
amount of microbial growth resulted. CCI was hired to complete the
mold remediation of this facility and to prepare the facility for
renovations. This project included the removal, cleaning, and
storage of the salvageable hotel furniture. The project was
completed in accordance with the specified schedule and final air
sampling was conducted.
Office Area Structural Drying; Atlanta, GA
CCI was called to respond to a sprinkler pipe freeze that caused
water damage to an 11,000-square foot office area. Upon inspection
there was visible mold and water, along with a large amount of
moisture trapped behind base boards and wall coverings. CCI
personnel dried the space using six Phoenix 200 refrigerant
dehumidifiers and 60 air movers to reduce the relative humidity of
the space. The extremely high moisture trapped in the drywall and
wall coverings compounded the difficulty of drying the space.
Therefore, CCI personnel removed the lower third of the wall
coverings before the commencement of drying. The wall coverings
were tacked to allow reinstallation of the coverings. The project was
completed on time and within schedule.
|
 |
 |