Environmental Civil Construction
Ward Transformer/Site Remediation/Demolition, Morrisville, NC
CCI was contracted to remove PCB-contaminated soil that was spread over
serveral acres. Contaminated and non contaminated materials were
excavated and stored on site at different locations. Contaminated
materials originally thought to be no more than 24 inches in depth
reached 10 feet or more in some areas.
The
contaminated soils were treated with a high temperature soil burner and
then stockpiled while crews demolished and decontaminated buildings on
site. Unusable materials were transported to an out of state location
for proper disposal. Once the site is completely remediated,
treated soil along with non toxic soils and topsoil brought in will be
spreadby over the entire site, landscaped and made ready for a suitable
buyer.
Landfill Design and Construction; Ft. Rucker, AL
CCI was awarded a Performance-Based Contract (PBC) for environmental
restoration services at the U.S. Army Aviation Center at Ft.
Rucker. The scope of services included the design and
implementation of a 30-acre former landfill cap (SWMU 2d). CCI
developed a Corrective Measures Implementation Plan for the Alabama
Department of Environmental Management; submitted the NOR permit;
prepared a Construction Best Management Practices Plan for the landfill
cover and borrow source.
Capping and
Closure
Construction of Engineered Caps; Mt. Pleasant, TN
CCI was contracted for the construction of engineered caps over former
phosphorus burial areas. The project was divided into multiple
Contractual Areas that were divided as North of Mt. Joy and South of
Mt. Joy Road.
By
dividing the Contractual areas, CDM was able to manage the logistics to
multiple work sites requiring the same fill soil and haul roads.
Following site preparation, CCI personnel placed fill to bring the
surface to cap elevations; placed a clay barrier layer; placed
vegetative soil cover; revegetated disturbed areas; performed
installation and maintenance of soil and erosion revegetated
surfaces; and provided surface drainage improvements.
Soil Excavation
Soil Excavation; Jacksonville, FL
CCI excavated 500 tons of petroleum-contaminated soil at a building to
the horizontal and vertical limits delineated by the client. The
project included loading of contaminated soils, traffic control
measures and backfilling to grade, and achieving the specified
compaction standards for the site. CCI excavated and loaded
approximately 600 tons of soils from an old service station excavation
in the general location.
The
project involved TPH and PAH contaminants. Several underground
utilities were not marked; therefore, personnel performed surgical
excavation of underground utilities.
AST/UST Removal and Installation
UST Removal and Installation for IRS; Atlanta, GA
CCI removed seven USTs that ranged in size from 1,000 gallon to 10,000
gallons. The scope involved the removal and re-installation of the tank
systems.
CCI
installed a petroleum hydrocarbon venting system in all tank holds.
Contaminated soils were excavated and transported to a local
landfill. Re-installation of the USTs included the installation
of double walled fiberglass inclusive of leak detection systems. The
newly installed USTs were equipped with an inclon sentinel system
capable of sending a leak detection report to a central office for
monitoring.
|